A project uses new, complex technology that most stakeholders do not understand. As a servant leader on this complex, innovative project, what should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Provide resources to train stakeholders on the new technology..
Why this is the answer
As a servant leader, the project manager's role is to support the team and stakeholders, enabling their success. Providing resources to train stakeholders on the new technology directly addresses their lack of understanding, fostering better engagement and decision-making. Escalating to senior management without first attempting a solution is premature and avoids the project manager's responsibility. Asking the sponsor to remove stakeholders is adversarial and counterproductive to collaboration. Requiring stakeholders to fund their own training shifts the project's responsibility to them and can create resentment, hindering project success.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed