A project using shared resources from other projects is due in three days when the team reports a delay because a component was not delivered on time due to competing priorities. What should the project manager have done to prevent this delay?
Choose an answer
Tap an option to check your answer.
Correct answer: Used the resource management plan to identify the impacts of the other projects.
Why this is the answer
The correct answer is "Used the resource management plan to identify the impacts of the other projects." The resource management plan outlines how resources will be acquired, allocated, monitored, and controlled. By proactively using this plan, the project manager could have identified potential conflicts or dependencies with other projects sharing the same component, allowing for mitigation strategies to be put in place before the delay occurred. "Updated the risk management plan and registered lessons learned for the project" is incorrect because these are reactive measures taken after an issue occurs, not preventative actions. "Reorganized the team for the project based on the work breakdown structure (WBS)" is incorrect as team organization, while important, doesn't directly address the external dependency of a shared component. "Maintained constant communication with the stakeholders of the other projects" is a good practice but without the framework of a resource management plan, it might not have been sufficient to identify and resolve the specific resource contention.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed