A project was completed within scope, schedule, and budget at the end of the final iteration. At the project celebration, a business stakeholder called the project a failure because it did not deliver business value. What should the project manager have done to prevent this perception?
Choose an answer
Tap an option to check your answer.
Correct answer: Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits.
Why this is the answer
The project manager should have defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits. This proactive approach ensures that the project's efforts are aligned with the organization's strategic goals and value expectations from the outset. By involving these critical stakeholders in prioritizing the backlog, the project manager could have ensured that features delivering tangible business value were given appropriate emphasis, preventing the perception of failure even if technical objectives were met. Including business stakeholders in the sprint review is beneficial for feedback but doesn't guarantee initial alignment on value. Conducting a closing survey is reactive and occurs too late to prevent the perception of failure. Ensuring a communications management plan informs stakeholders of success focuses on reporting, not on the fundamental alignment of project outputs with business value.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed