A project with a fixed timeline is starting its first of six iterations, but the team lacks the required skills. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Add a subject matter expert (SME) to the project team..
Why this is the answer
Adding a Subject Matter Expert (SME) directly addresses the identified skill gap, which is crucial for a project with a fixed timeline. An SME can provide the necessary expertise, guide the team, and ensure the work is completed correctly and efficiently within the iteration. Filling the skill gap personally is not scalable or sustainable for a project manager, whose primary role is to lead and manage, not execute all technical tasks. Allowing the team to proceed without addressing the skill gap will likely lead to delays, quality issues, and failure to meet the fixed timeline. Inviting stakeholders to discuss a mitigation plan is a reactive step; the immediate and proactive solution is to acquire the necessary skills for the team.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed