A remodel project lacks records of the original product design and execution. Stakeholders doubt success without this information and hesitate to support the project. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.
Why this is the answer
The project manager should acknowledge stakeholder concerns through open dialogues and realign the project. This approach directly addresses the root cause of their hesitation: the lack of original design and execution records leading to doubts about success. By engaging in dialogue, the project manager can understand their specific worries and incorporate their requirements and lessons learned from similar past projects into the current plan. This builds trust and support. Creating a communication plan (B) is reactive and doesn't address the underlying issue of missing information or stakeholder doubt. Describing risks (C) without a plan to mitigate them will likely increase, not decrease, stakeholder hesitation. Requesting larger reserves (D) is a financial and schedule adjustment that doesn't solve the core problem of missing historical data or stakeholder confidence.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed