A stakeholder reports several compliance gaps and offers suggestions to resolve them. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Discuss the suggestions with the staff responsible for the compliance issues..
Why this is the answer
The project manager should discuss the suggestions with the staff responsible for the compliance issues because this directly engages the individuals who can implement the solutions and improve compliance. This approach fosters ownership and facilitates immediate action to address the gaps. Reviewing with the sponsor is important for strategic oversight but doesn't directly solve the operational issue. Recording in lessons learned is valuable for future projects but doesn't resolve the current compliance gaps. Identifying coaching opportunities might be a secondary benefit, but the primary goal is to fix the compliance issues, which requires direct engagement with the responsible staff.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed