A strategic, competitive-advantage healthcare project is in testing after 6 months and team morale is low because of the schedule. What can the project manager do to motivate the team?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the functional (horizontal) managers to recognize team members and arrange rewards or promotions upon project completion..
Why this is the answer
The best option is to meet with functional managers to arrange recognition and rewards. This directly addresses low morale by offering tangible future benefits (rewards, promotions) and acknowledges their hard work, which is a strong motivator. Functional managers are typically responsible for career progression and resource allocation, making them the appropriate stakeholders for such discussions. Continuing to work without addressing morale will likely lead to burnout and decreased performance. Requesting a monetary reward for the team might be difficult to implement quickly and may not address the underlying morale issues if the team feels unappreciated or overworked. Requesting a schedule extension for time off, while potentially helpful, might not be feasible for a strategic, competitive-advantage project and could delay critical deliverables.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed