A supplier says producing the required quantity of a key component will take an additional month, but an important milestone is due in a week. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline..
Why this is the answer
The project manager should first ask the vendor if a minimally sufficient quantity of materials can be produced in time. This is the most immediate and practical step to mitigate the impact on the upcoming milestone. It explores a potential solution within the existing vendor relationship before escalating or seeking new suppliers. Performing market research or involving the legal department are more drastic, time-consuming actions that might be necessary later if this initial approach fails. Submitting a change request to extend the deadline without first exploring options to meet it is premature and reactive, rather than proactive problem-solving.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed