A team is finishing the third release for a stakeholder demo. The subcontractor for developers reports cash-flow problems and cannot provide the same resources for future iterations. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Analyze the impact against the release plan if the blocker is not addressed..
Why this is the answer
The project manager's immediate next step should be to analyze the impact of the subcontractor's issue on the release plan. This allows for an understanding of the potential consequences (e.g., delays, scope reduction, quality issues) before deciding on a course of action. Without this analysis, any subsequent decisions would be uninformed. Creating a risk register is a good practice, but the immediate need is impact analysis. Escalating to the sponsor or working with the product owner are potential later steps, but only after understanding the problem's magnitude.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed