A team reused a report format from a previous project, but new stakeholders do not fully understand the project's status from those reports. How should the project manager address this going forward?
Choose an answer
Tap an option to check your answer.
Correct answer: Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan..
Why this is the answer
The correct answer is to employ Monitor Communications techniques because this process involves evaluating the effectiveness of communication throughout the project. The new stakeholders' inability to understand the reports indicates a breakdown in effective communication. Monitoring communications can identify this deficiency and lead to necessary adjustments. These adjustments could include changes to the communications management plan, such as updating report formats or communication methods to better suit the new stakeholders' needs. Adding the issue to the issue log is a reactive step and doesn't address the underlying process of identifying and resolving communication problems. Creating a fishbone diagram is a root cause analysis tool, but the immediate need is to monitor and adjust communication effectiveness, which is part of Monitor Communications. Sharing the existing communications management plan and reminding stakeholders of agreed-upon templates is unhelpful since the current plan is demonstrably ineffective for the new stakeholders.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed