A visual management tool revealed a dependency: one team's domain knowledge must be shared with another to maintain deliverables. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the respective teams to schedule knowledge-sharing sessions..
Why this is the answer
The project manager should ask the teams to schedule knowledge-sharing sessions. This directly addresses the identified dependency by facilitating the necessary transfer of domain knowledge, ensuring deliverables can be maintained. This is a practical and collaborative approach that empowers the teams to resolve the issue themselves, with the project manager's guidance. Removing the dependency is often not feasible, as it implies altering project scope or deliverables, which can have significant negative impacts. Reassigning team members might disrupt team dynamics and create new knowledge gaps elsewhere. Combining teams could lead to inefficiencies, communication overhead, and loss of specialized focus, which is an overreaction to a knowledge-sharing need.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed