After a status meeting the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project's status?
Choose an answer
Tap an option to check your answer.
Correct answer: Behind schedule.
Why this is the answer
A negative schedule variance (SV) indicates that the project is behind schedule. Schedule Variance is calculated as Earned Value (EV) minus Planned Value (PV). If EV < PV, then SV is negative, meaning less work has been completed than planned by this point. While being under budget and having positive quality checks are favorable, the negative schedule variance directly addresses the schedule status. "Ahead of schedule" would be indicated by a positive SV, and "on schedule" by an SV of zero. "Stopped" is incorrect as there's no information to suggest the project has ceased.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed