After completing the first phase, the project manager declared success because the project was on time, on budget, and on scope. The sponsor disagreed, saying benefits like reduced product cost and improved system response time weren't achieved. What likely caused this?
Choose an answer
Tap an option to check your answer.
Correct answer: The acceptance criteria were not accurately defined..
Why this is the answer
The correct answer is that acceptance criteria were not accurately defined. The scenario highlights a disconnect between the project manager's definition of success (on time, on budget, on scope) and the sponsor's definition (achieved benefits like reduced product cost and improved system response time). This indicates that the criteria for accepting the project's deliverables, particularly in terms of the value they were expected to deliver, were either missing or poorly articulated. Acceptance criteria should clearly state the conditions that must be met for deliverables to be accepted, including the expected benefits. The change control plan not being followed is incorrect because the issue isn't about changes to the project, but rather the initial definition of success. "Those benefit items were not included in the project management plan" is too broad; while they might not have been, the core issue is the criteria for acceptance of what was included. "The benefits should have been managed at the organizational level" is partially true for strategic benefits, but project acceptance criteria must still reflect how the project contributes to those benefits.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed