After presenting the project schedule, key stakeholders request the project be completed two months earlier than planned. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Hold a stakeholder meeting to align timelines and scope expectations.
Why this is the answer
The correct answer is to hold a stakeholder meeting to align timelines and scope expectations. This is the most appropriate first step because a change request of this magnitude (shortening the schedule by two months) requires a thorough analysis of its impact on all project constraints: scope, cost, quality, and resources. A meeting allows the project manager to facilitate a discussion with stakeholders about the trade-offs involved, ensuring everyone understands the implications of an accelerated schedule. Crashing the schedule (option B) or reducing scope (option D) are potential solutions, but they should only be considered after discussing the implications with stakeholders and gaining their agreement. Adjusting the cost management plan (option C) might be part of a crashing strategy, but it's not the initial action. The project manager must first engage stakeholders to understand their priorities and collectively decide on the best path forward, balancing all project constraints.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed