After removing impediments and getting the project back on track, the team finds a previously resolved impediment has recurred. The same mitigation tasks used before no longer produce the same results. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Reassess the issue as part of monitoring and controlling..
Why this is the answer
The correct answer is "Reassess the issue as part of monitoring and controlling." When a previously resolved impediment recurs and prior solutions are ineffective, it indicates a need for a deeper analysis. Reassessing the issue within the monitoring and controlling process group allows the project manager and team to understand the root cause of the recurrence, evaluate new options, and develop an effective, lasting solution. Escalating to the sponsor (option A) is premature; the team should first attempt to resolve the issue themselves. Implementing generic mitigation plans from OPAs (option B) is unlikely to work, as the previous specific mitigation failed. Using the contingency budget for schedule compression (option C) addresses a symptom (schedule delay) but not the underlying impediment, and it might not be the most effective or appropriate solution without understanding the root cause.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed