An agile database migration affects almost all business units. Despite efforts to finish before the platform's end-of-support date, a new impediment means the old platform must be used for another year at higher support cost. What should the product owner do?
Choose an answer
Tap an option to check your answer.
Correct answer: Reprioritize the backlog using value and cost of delay divided by duration..
Why this is the answer
The product owner should reprioritize the backlog using value and cost of delay divided by duration. This method, often called Weighted Shortest Job First (WSJF), helps identify which features deliver the most value fastest, considering the financial impact of delaying them. Given the increased support costs and the need to extend the old platform's use, optimizing for economic value is crucial. Switching to a predictive approach is unlikely to resolve delays and contradicts agile principles. Reprioritizing based solely on story size and available skills ignores the critical financial implications. Removing low-value items might be part of a larger strategy, but it doesn't address the immediate need to maximize value delivery given the new cost structure.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed