An agile project has a wide range of product features for different user profiles, making common acceptance criteria hard to define. How can the project manager ensure appropriate acceptance criteria are applied to each feature?
Choose an answer
Tap an option to check your answer.
Correct answer: Integrate acceptance criteria review into the definition of ready (DoR) for each feature and include associated tests in the feature’s definition of done (DoD)..
Why this is the answer
The correct option ensures that acceptance criteria are clearly defined and verified for each feature, which is crucial when features have diverse user profiles. Integrating acceptance criteria review into the Definition of Ready (DoR) means that before work begins on a feature, its acceptance criteria are well-understood and agreed upon. Including associated tests in the Definition of Done (DoD) ensures that these criteria are met before the feature is considered complete. Defining acceptance criteria only after user feedback (incorrect option 2) is too late, as the team needs to know what to build and test upfront. Including specific tests in the DoR and acceptance criteria in the DoD (incorrect option 3) reverses the logical flow; acceptance criteria should guide the tests, not the other way around. Using the broadest acceptance criteria (incorrect option 4) would fail to address the specific needs of diverse user profiles, leading to an inadequate quality baseline for individual features.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed