An agile project is in iteration 8 of 16. After the last iteration review, the security department gave feedback about regulatory requirements the project must meet. Which two actions should the project manager take? (Choose two.)
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the security department for details about regulations., Ask the team members to analyze the impact of including this regulation..
Why this is the answer
The project manager should first gather more details from the security department about the regulatory requirements to fully understand their scope and implications. This ensures clarity and accuracy before proceeding. Concurrently, the project manager should ask the team members to analyze the impact of these new regulations. This analysis will help determine the effort, dependencies, and potential changes needed for the project, informing subsequent planning and prioritization. Adding the requirements directly to the product backlog without understanding the details or impact is premature. Asking stakeholders to assign a priority to the regulation is also premature; the team needs to understand the regulation and its impact before effective prioritization can occur. Including the requirements in the next iteration without analysis or proper backlog integration could disrupt the sprint and lead to inefficient work.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed