An agile project is in its second iteration of six. A key stakeholder (marketing director) requests a high-level project report. What should the project lead do?
Choose an answer
Tap an option to check your answer.
Correct answer: Develop the requested report based on the iteration information..
Why this is the answer
The project lead should develop the requested report based on available iteration information. In agile, transparency and stakeholder collaboration are key. Providing a report, even if high-level, demonstrates responsiveness and keeps the stakeholder informed, fostering trust. Asking the product owner to create the report might delay the response and is the project lead's responsibility to facilitate. Explaining that indicators are reported by iteration or stating a new report will be produced later might be perceived as unhelpful or dismissive, potentially frustrating the stakeholder. The project lead should proactively meet stakeholder needs when possible, using current, readily available data.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed