An agile project manager notices the team has lost momentum over recent iterations. Which two tools should be used to analyze team performance? (Choose two.)
Choose an answer
Tap an option to check your answer.
Correct answer: Burndown chart, Cumulative flow diagram of completed features.
Why this is the answer
A burndown chart tracks remaining work against time, clearly showing if the team is on track to complete the iteration's scope. A flattening line indicates a loss of momentum. A cumulative flow diagram (CFD) visualizes workflow, showing work in progress, completed work, and lead times. A widening gap between the "in progress" and "completed" lines, or a flattening "completed" line, signifies a slowdown or bottleneck, indicating lost momentum. The product backlog burnup chart tracks overall project progress, not iteration-level momentum. A WBS defines scope but doesn't track performance. A project schedule tracks planned activities but isn't an agile performance metric for team momentum.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed