An agile project manager wants to convert the requirements document into epics, capabilities, features, and stories. Over how many iterations should the project manager estimate story duration?
Choose an answer
Tap an option to check your answer.
Correct answer: One iteration.
Why this is the answer
In agile frameworks, stories are the smallest units of work, typically designed to be completed within a single iteration (or sprint). This practice ensures that work is delivered incrementally, allows for frequent feedback, and enables teams to adapt quickly to changing requirements. Estimating story duration for more than one iteration would contradict the core agile principle of delivering small, manageable chunks of work and would essentially turn a story into a larger feature or epic, which should be broken down further. Therefore, a story's duration should always be estimated for one iteration.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed