An agile team completed 9 of 10 sprint stories. At the retrospective, some members said they completed all their stories, but one team member did not finish a story. What should the agile leader do?
Choose an answer
Tap an option to check your answer.
Correct answer: Emphasize that while each person is accountable for their stories, the team is collectively responsible for completing the sprint..
Why this is the answer
The correct answer emphasizes a core agile principle: collective ownership. While individuals are accountable for their tasks, the team shares responsibility for the sprint's success or failure. This approach fosters collaboration and mutual support, preventing a blame culture and encouraging the team to help each other. "Propose assigning stories at sprint start based on individuals' strengths" is incorrect because agile teams typically self-organize and pull stories, rather than having them assigned, and this doesn't address the collective responsibility aspect. "Work with the product owner to remove the story from the sprint because story points are indivisible" is incorrect; while story points are a relative measure, removing a story doesn't solve the underlying team dynamic issue and might hide the problem. "Ask the team to address this during the next sprint planning" is incorrect because the retrospective is precisely the forum for inspecting and adapting team processes and performance.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed