An agile team has started a new project. When should the project manager schedule the team's first retrospective?
Choose an answer
Tap an option to check your answer.
Correct answer: When the team reaches a major milestone..
Why this is the answer
The first retrospective should be scheduled when the team reaches a major milestone, such as the end of the first iteration or sprint. This allows the team to reflect on their initial processes, identify what went well, and pinpoint areas for improvement early in the project lifecycle. Waiting for "a few weeks" is too vague and might delay critical feedback. Waiting for a "monumental increment" or "release" could mean delaying feedback until significant issues have compounded. While progress is good, retrospectives are for continuous improvement, not just when problems arise.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed