An agile team is trying to crash the schedule by assigning multiple resources, but the technical environment allows only one resource per feature. The team plans to upgrade the environment but cannot agree on the way forward. What should you do first?
Choose an answer
Tap an option to check your answer.
Correct answer: Conduct a consensus-building session to decide how to approach the next set of work..
Why this is the answer
The team is experiencing a conflict regarding how to proceed with upgrading their technical environment. A consensus-building session is the most appropriate first step because it directly addresses the disagreement among team members. This session allows for open discussion, exploration of different perspectives, and collaborative decision-making, which is crucial for agile teams. Adding the conflict to a daily standup agenda is insufficient as standups are for quick updates, not in-depth problem-solving or conflict resolution. Holding a planning session without first resolving the underlying disagreement about the approach would be premature and likely unproductive. Escalating to the product owner should be a last resort; the team should first attempt to resolve internal conflicts independently, aligning with agile principles of self-organizing teams.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed