An incremental project with a colocated team uses a Kanban board to visualize WIP. A key external stakeholder demands that all activities stop until a status report is distributed. What should the project manager have done to avoid this?
Choose an answer
Tap an option to check your answer.
Correct answer: Send weekly status update reports to all stakeholders..
Why this is the answer
Sending weekly status update reports to all stakeholders is the most effective way to prevent such a demand. Regular, proactive communication keeps stakeholders informed about project progress, risks, and accomplishments, reducing their need to intervene or demand immediate updates. This builds trust and manages expectations. Storing documentation in a shared folder is good for transparency but doesn't guarantee stakeholders will review it or understand the current status without a summary. Organizing monthly meetings might not be frequent enough for some stakeholders, leading to anxiety and ad-hoc requests. Inviting all stakeholders to daily standups is generally not practical or efficient; standups are for the delivery team to synchronize and plan, not for broad stakeholder updates.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed