An industrial plant will add capacity by installing a new machine and updating production software while production continues. The software update will use agile methods; machine procurement, installation, and integration will use predictive methods. What communications should the project manager include in the schedule management plan to keep the project on schedule?
Choose an answer
Tap an option to check your answer.
Correct answer: Weekly co-located meetings with relevant stakeholders.
Why this is the answer
The project combines agile and predictive approaches, requiring frequent and adaptable communication. Weekly co-located meetings foster direct interaction, quick decision-making, and immediate issue resolution, which is crucial for maintaining schedule in a hybrid environment, especially with ongoing production. This approach supports the agile software development's need for rapid feedback and the predictive machine installation's need for coordinated efforts. Biweekly calls are less frequent and may delay issue resolution. Weekly one-on-one meetings are inefficient for coordinating multiple stakeholders across different workstreams. Biweekly written reports are passive and lack the immediacy and collaborative problem-solving benefits of face-to-face interaction.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed