An integrated project involves both hardware and software and the sponsor has approved the schedule management plan. The team assessed the product's functional feasibility and accelerated testing. As a servant leader, what should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Support the team as necessary to find the minimum viable product (MVP)..
Why this is the answer
As a servant leader, the project manager's primary role is to support the team. Given the team has already assessed functional feasibility and accelerated testing, the next logical step in an integrated project, especially with a focus on value delivery, is to identify and deliver the Minimum Viable Product (MVP). Supporting the team in this endeavor aligns with agile principles and servant leadership, ensuring the team has the resources and guidance to achieve this goal. Amending the budget for MVP testing is premature; the focus should first be on defining the MVP. Submitting a change request for accelerated testing is unnecessary as the team has already performed this assessment. Developing the product per the schedule without considering the MVP could lead to delivering unnecessary features or delaying early value delivery.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed