An organization adopting agile used to send weekly progress emails to stakeholders. The development team now uses a burndown chart and a Kanban board to show progress. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Give stakeholders access to the burndown chart and Kanban board and ask them to use these tools..
Why this is the answer
The correct answer is to give stakeholders access to the burndown chart and Kanban board and ask them to use these tools. In an agile environment, transparency is key. These tools provide real-time, visual updates on project progress, allowing stakeholders to self-serve information and understand the team's velocity and workflow. This approach fosters collaboration and reduces the need for frequent, formal progress reports, aligning with agile principles. Using them as supplementary communication (first incorrect option) misses the opportunity to leverage their full potential for transparency and stakeholder engagement. Training stakeholders (third incorrect option) is a good idea, but simply giving access and encouraging use is the immediate and most direct action to shift communication practices. Continuing only traditional channels (fourth incorrect option) defeats the purpose of adopting agile tools and practices.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed