An organization experienced only with predictive projects is about to start a complex research project and the project manager recommends a hybrid approach. How should the project manager introduce the hybrid approach to the organization?
Choose an answer
Tap an option to check your answer.
Correct answer: Demonstrate the benefits of a hybrid approach to key stakeholders to secure their support..
Why this is the answer
The correct answer is to demonstrate the benefits of a hybrid approach to key stakeholders to secure their support. For a new approach, especially in an organization accustomed to predictive methods, gaining stakeholder buy-in is crucial for successful adoption and project success. Demonstrating the value proposition helps overcome resistance and builds confidence. Notifying the project team is premature without stakeholder approval and doesn't address organizational change. Sending a request to the PMO is a good step, but it's more effective after initial stakeholder alignment. Creating a project change request is also a later step; the initial focus should be on building understanding and support for the new methodology itself.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed