An organization imports many materials for a product build, but global shipping delays have prevented arrival of essential items, blocking completion for the upcoming release. The project manager is discussing options with stakeholders. What should the project manager recommend?
Choose an answer
Tap an option to check your answer.
Correct answer: Investigate whether local suppliers can provide the materials on time..
Why this is the answer
The project manager should investigate local suppliers because this directly addresses the critical path issue of missing materials and potential delays. This proactive approach seeks to mitigate the risk by finding an alternative source, allowing the project to potentially stay on schedule. Asking marketing to launch a campaign for in-stock products is a business decision, not a project management solution for the current problem. Updating the plan for furloughs is a reactive cost-cutting measure that doesn't solve the material shortage and could negatively impact morale and future project phases. Meeting with engineering for in-house manufacturing is a long-term solution that is unlikely to resolve an "upcoming release" issue due to the time required for setup and production.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed