An organization is transitioning to agile and the development team proposes using a burndown chart to show progress to stakeholders. What should the project manager do to ensure effective communication throughout the project?
Choose an answer
Tap an option to check your answer.
Correct answer: Develop a communications management plan for each category in the stakeholder register..
Why this is the answer
The correct answer is to develop a communications management plan for each category in the stakeholder register. This ensures that communication methods, frequency, and content are tailored to the specific needs and preferences of different stakeholder groups, promoting effective information exchange. Simply adopting the burndown chart as the sole communication channel is insufficient as different stakeholders require different types of information and levels of detail. Including the burndown chart in a monthly report is a good start but doesn't address the diverse communication needs of all stakeholders. Delaying the suggestion because the organization lacks a defined agile methodology is counterproductive; the project manager should proactively establish communication strategies regardless of the organizational agile maturity.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed