An unforeseen event halted public works for four weeks, causing critical path activities to fall behind. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the project management plan to determine the impact of the possible delay..
Why this is the answer
The correct answer is to review the project management plan to determine the impact of the possible delay. Before taking any action, a project manager must understand the full scope of the problem. This involves analyzing the project schedule, cost baseline, risk register, and other relevant components of the project management plan to assess the impact of the four-week halt. Only after this analysis can the project manager make informed decisions about potential solutions. Adding four weeks and requesting resources prematurely assumes a solution without understanding the full impact. Asking the sponsor for a special permit might be a viable solution, but it's not the immediate first step; the impact must first be understood. Crashing the resource management plan is not a standard project management term; crashing is a schedule compression technique, and it's premature to apply any solution before assessing the impact.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed