As part of company planning for team capacity building, the project manager must provide a list of required trainings for the project team. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the project pipeline, identify competency gaps for execution, and decide on the required trainings..
Why this is the answer
The correct answer emphasizes a forward-looking approach to team capacity building. Reviewing the project pipeline allows the project manager to proactively identify future project needs and the competencies required for successful execution. By identifying these competency gaps before execution begins, the project manager can plan and implement relevant trainings to ensure the team is prepared. The other options are less comprehensive or proactive: "Review competency gaps found during execution" is reactive; training should ideally occur before gaps impact performance. "Review the project schedule and team performance, and determine needed soft skills" is too narrow; it focuses only on soft skills and doesn't consider the full scope of future project requirements. "Review recent performance, identify competency gaps" is also reactive and focuses on past performance rather than future needs.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed