As the project manager builds the initial project baseline, a functional manager submits a change request. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Analyze the impact of the change request on the project..
Why this is the answer
Analyzing the impact of the change request is the correct first step. Before any decision can be made, the project manager needs to understand how the proposed change will affect the project's scope, schedule, cost, quality, resources, and risks. This analysis provides the necessary information to make an informed decision and to present to the change control board (CCB) if the change is deemed viable. Requesting formal approval from the CCB is premature without a prior impact analysis. Discussing the request is part of the analysis but not the complete first step. Rejecting the request immediately is inappropriate without understanding its potential value or impact.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed