Assess the statement: "The Burnup widget measures the elapsed time from work item creation to completion." If the statement is accurate, select 'No adjustment required.' If it is inaccurate, select the correct term.
Choose an answer
Tap an option to check your answer.
Correct answer: Lead time.
Why this is the answer
The statement is inaccurate. The Burnup widget tracks the total work completed against the total scope over time, indicating progress towards a goal, not the time taken for individual items. Lead time is the correct term for measuring the elapsed time from when a work item is created (or requested) to when it is completed. Test results trend displays the pass/fail rate of tests over time. Burndown measures the remaining work against the remaining time, showing progress towards zero remaining work.