At a large manufacturing company the change control board deferred some change requests. The project manager needs to communicate those deferred requests to stakeholders. Which document should be used to communicate them?
Choose an answer
Tap an option to check your answer.
Correct answer: Change log.
Why this is the answer
The change log is the correct document because it records all change requests, their status (approved, deferred, rejected), and their impact. It serves as a comprehensive record for communicating the disposition of changes to stakeholders. The risk log tracks potential future events and their impact, not the status of change requests. The backlog is a prioritized list of work to be done, often used in agile methodologies, but it doesn't specifically detail the disposition of formal change requests. The issue log tracks problems or obstacles encountered during the project, not the status of proposed changes.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed