At a recent steering committee meeting, the project sponsor requested adding a major feature to the final product. After consulting the team, you determine the change will significantly affect the original delivery date and budget. What should the project manager do to evaluate priorities and meet the new objective?
Choose an answer
Tap an option to check your answer.
Correct answer: Communicate the impact and negotiate the required time and resources with the stakeholder..
Why this is the answer
The project manager's primary responsibility in this situation is to manage stakeholder expectations and the project scope. Communicating the impact of the requested change on the delivery date and budget, then negotiating with the sponsor, ensures transparency and allows for an informed decision on how to proceed. This aligns with the principle of managing changes through a formal process. Submitting a change order request to the PMO is a subsequent step, but first, the project manager must engage with the sponsor to discuss the implications. Initiating a crashing routine or asking the team to work overtime are potential solutions that might be discussed after the impact is communicated and negotiation occurs, but they are not the immediate first step for evaluating priorities and meeting the new objective. These actions also carry their own risks and costs that need to be weighed.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed