At daily standups, team members repeatedly ask which tasks to prioritize. How should the project manager ensure the team remains fully productive?
Choose an answer
Tap an option to check your answer.
Correct answer: Work with the product owner to ensure the project backlog is prioritized..
Why this is the answer
The correct answer is to work with the product owner to ensure the project backlog is prioritized. In Agile frameworks, the Product Owner is responsible for maximizing the value of the product and managing the product backlog, which includes prioritizing items. If team members are consistently asking for prioritization, it indicates a gap in this process. The Project Manager (or Scrum Master in Scrum) facilitates this collaboration to ensure the team has a clear, prioritized list of tasks, enabling them to pull work efficiently and remain productive. Reviewing the project backlog during the standup is inefficient and not the primary purpose of a standup. Encouraging team members to prioritize the product backlog is incorrect; prioritization is the Product Owner's role. Ensuring team members work according to the project plan is too rigid for Agile and doesn't address the root cause of unclear priorities.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed