At project start, the project manager is asked to provide HR with an evaluation of each team member's performance to be delivered at project end. How should the project manager approach this request?
Choose an answer
Tap an option to check your answer.
Correct answer: Define objective, measurable performance indicators for evaluating team members and share them with the team..
Why this is the answer
The project manager should define objective, measurable performance indicators and share them with the team. This proactive approach ensures transparency and fairness, allowing team members to understand the expectations and criteria for their evaluation from the outset. This aligns with best practices for performance management and team development. Providing confidential evaluations at project end without prior communication is unfair and can lead to resentment. Asking team members how they want to be evaluated is not the project manager's responsibility; the PM must establish consistent, objective criteria. Evaluating solely on project objectives doesn't account for individual contributions or performance nuances, as a project can fail for reasons beyond an individual's control, or succeed despite poor individual performance.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed