At the last sprint review, the main stakeholder complained the product lacks many expected features. The team says every increment met the acceptance criteria and the stakeholder approved them. The project's CPI is 1.15 and SPI is 1.43. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Analyze the reason for the gap in understanding with both sides and negotiate a solution..
Why this is the answer
The correct answer is to analyze the reason for the gap in understanding and negotiate a solution. This approach addresses the root cause of the stakeholder's dissatisfaction, which stems from a misalignment between expectations and delivered features, despite formal acceptance. The strong CPI and SPI indicate the project is performing well against its current plan, suggesting there's capacity to address the issue if a solution is negotiated. Asking the team to make changes without understanding the root cause is premature and could lead to scope creep without stakeholder buy-in. Asking for a change request immediately places the burden on the stakeholder and doesn't address the underlying communication breakdown. Closing the project based solely on met acceptance criteria ignores the stakeholder's current dissatisfaction and the potential for a failed product, despite technical compliance.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed