During a large project, a stakeholder identifies a risk that was not previously recorded. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.
Why this is the answer
The correct approach is to add the newly identified risk to the risk register and then reevaluate the entire register with the project team and relevant stakeholders. This ensures a comprehensive and collaborative update to the risk management plan. Simply confirming the register is complete is dismissive and ignores a valid input. Performing a risk analysis with only one stakeholder is insufficient; a broader team perspective is needed for accurate assessment and planning. Communicating directly to the steering committee and requesting a mitigation plan from senior management bypasses the project team's responsibility for initial risk analysis and response planning.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed