During a major cost-cutting initiative, senior management requests a report showing the remaining work for outstanding projects. Which tool should the project manager use?
Choose an answer
Tap an option to check your answer.
Correct answer: Burndown chart.
Why this is the answer
A burndown chart visually represents the remaining work over time, making it ideal for showing senior management the progress and outstanding tasks in a cost-cutting initiative. It clearly depicts the amount of work left to be done against the time available. Forecast estimation is a technique, not a tool, used to predict future project performance. Earned Value (EV) measures the value of work completed but doesn't directly show remaining work in a simple, visual format for this purpose. A cumulative flow diagram tracks work in progress and completed work but is more complex and less direct for simply showing "remaining work" than a burndown chart.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed