During a major product upgrade, the project manager learns that resources originally promised to the project are being reassigned to a higher-priority project. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Perform an impact analysis to see the effect on the project.
Why this is the answer
When resources are unexpectedly reallocated, the project manager's immediate priority is to understand the consequences for their project. Performing an impact analysis involves assessing how the loss of resources affects the project schedule, budget, scope, quality, and risks. This data is crucial for informed decision-making and communicating the situation to stakeholders. Examining ways of modifying the scope is premature without understanding the full impact. Adopting a resource leveling procedure is not applicable here, as resources are being removed, not just unevenly distributed. Retrieving documentation is a good step for verification but doesn't address the immediate need to understand the impact of the change.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed