During a project to develop a new pharmaceutical product, the project manager learns of a change in government regulations affecting project materials. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Study the new regulations with the team and evaluate if there is any impact on the project variables..
Why this is the answer
The project manager's first step should be to understand the impact of the new regulations. Studying the regulations with the team allows for a comprehensive evaluation of their effects on project scope, schedule, cost, quality, and resources. This analysis provides the necessary information to determine the appropriate subsequent actions. Updating the contingency plan is premature without first understanding the full impact of the change. Meeting with stakeholders to update the risk register and risk management plan is also a later step, after the initial impact assessment has been completed. Reviewing procurement documentation and modifying requirements might be necessary, but only after the impact on project variables has been assessed and confirmed.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed