During a review, the project manager finds that a formerly high-performing team member failed to complete their work on time. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Talk to the team member to determine why their performance changed..
Why this is the answer
The best first step is to talk directly with the team member. This allows the project manager to understand the root cause of the performance change, which could be personal issues, project-related challenges, or resource constraints. This approach is empathetic and aligns with effective team management, fostering trust and open communication. Speaking with the team member's manager or HR is premature and escalatory without first understanding the situation from the team member's perspective. Assigning less demanding tasks without understanding the problem might not address the core issue and could be perceived negatively by the team member.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed