During an agile project, the team lost a resource and new requirements were added to the backlog. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Reevaluate the backlog priority with the product owner since the velocity has been impacted..
Why this is the answer
The correct answer is to reevaluate the backlog priority with the product owner because losing a team member and adding new requirements directly impacts the team's capacity (velocity). The Product Owner is responsible for maximizing the value of the product, which includes prioritizing the backlog to reflect these changes and ensure the most valuable items are still being worked on. Reevaluating the current iteration scope to maintain the same velocity and timeline is incorrect because the team's capacity has changed, making the original scope unrealistic. Reevaluating the velocity because the iteration duration will be impacted by new requirements is incorrect; velocity reflects the amount of work completed in an iteration, not the duration itself. Reevaluating the project schedule because velocity will be affected by the lost resource is also incorrect because in agile, the focus is on adapting to change and delivering value iteratively, not rigidly adhering to a fixed schedule that may no longer be feasible.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed