During an annual review of the system design, an engineer identified a few issues with the currently released design. Which of the following should be performed next according to best practices?
Choose an answer
Tap an option to check your answer.
Correct answer: Change control process.
Why this is the answer
The correct answer is Change control process. When an engineer identifies issues with a released system design during an annual review, the next step is to initiate a change control process. This structured process ensures that any proposed modifications are properly documented, reviewed, approved, tested, and implemented, minimizing negative impacts and maintaining system integrity. Risk management process is a broader activity that identifies, assesses, and mitigates risks, but it's not the direct next step for addressing identified design issues in an already released system. The Product design process is typically completed before release and focuses on initial design creation, not post-release modifications. A Design review process is part of the initial design phase or a periodic check, but once issues are found and changes are needed for a released product, the change control process takes over.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed