During execution of a facility expansion, connecting new equipment power to Point A requires a long cable. The construction team suggests connecting to Point B to save money. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Perform a cost-benefit analysis to evaluate using the Point B option..
Why this is the answer
The project manager should perform a cost-benefit analysis to evaluate the Point B option. This allows for a structured assessment of the proposed change, considering both the potential cost savings and any associated risks or impacts on quality, schedule, or scope. Simply logging an issue and requesting more budget doesn't address the proposed solution. Asking the construction team to decide delegates a project management responsibility and could lead to suboptimal decisions without a full understanding of project impacts. Using the Point B option immediately without analysis is premature and could introduce unforeseen problems, as cost savings alone do not guarantee it's the best option.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed