During execution, the project manager finds a key deliverable missing from the scope of work. After investigation, the team determines the missing deliverable will impact the critical path. What should the project manager do to avoid future delays?
Choose an answer
Tap an option to check your answer.
Correct answer: Submit a change request..
Why this is the answer
The correct answer is to submit a change request. Since a key deliverable is missing from the scope of work and impacts the critical path, it represents a change to the project's baseline. All changes to scope, schedule, or cost baselines must be formally requested, reviewed, and approved through the integrated change control process. This ensures the change is properly documented, assessed for its impact, and authorized before implementation. Adding additional resources might help if the issue were a resource constraint, but it doesn't address the fundamental problem of a missing deliverable from the scope. Updating the scope of work directly without a change request bypasses the formal change control process, which is critical for maintaining project integrity and stakeholder alignment. Reviewing the risk management plan is important for proactive risk identification, but in this scenario, the issue has already occurred and requires a formal change process, not just a review of potential future risks.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed