During execution, the project manager notices work performance reports have worsened dramatically in under two weeks. The team in Country A says holidays in Country B caused delays that affected their work. How should the project manager respond?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the risk management plan to evaluate the probability and impact of these delays.
Why this is the answer
The correct response is to review the risk management plan because the situation describes an issue that has arisen from a previously unidentified or unmanaged risk (holidays in Country B affecting Country A's work). The risk management plan provides the framework for identifying, analyzing, and responding to risks. By reviewing it, the project manager can determine if this risk was anticipated, if a response was planned, and how to proceed with risk response planning or contingency plans. Implementing crashing or fast-tracking (schedule compression techniques) without understanding the root cause and impact from a risk perspective could be premature and ineffective. Performing conflict management is not the primary immediate step; the issue is a delay caused by external factors, not necessarily an interpersonal conflict requiring conflict management techniques.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed